Substation of Irapé

Substation of Irapé 230 kv

CONTRACTOR: Siemens

OWNER: Transmineira

2016 – Irapé, Minas Gerais

Complete installation of an Air Reactor Bank – 230 KV – 13.3 Mvar at the Irapé Substation, by providing services, supplying materials, carrying out civil works, electromechanical assembly and commissioning support.

Scope Details

Civil

Eletromechanical